THUMB RULES FOR CIVIL WORKS LABOUR PRODUCTIVITY S.SUDHA VELAN B.E (CIVIL)

THUMB RULES FOR CIVIL WORKS LABOUR PRODUCTIVITY Bar bending Works (Reinforcement) Slab & Beams -1 Fitter +1.5 Helper – 170 Kg/day Footing - 1 Fitter +1.5 Helper – 200 Kg/day

THUMB RULES FOR CIVIL WORKS LABOUR PRODUCTIVITY Form Work (Shuttering) – Fixing & Removal Slab & Beams -1 Carpenter +1.5 Helper – 5 Sqm /day Footing - 1 Carpenter +1.5 Helper – 7 Sqm /day Column Box Fixing -1 Carpenter + 2 Helpers- 20 Sqm/day Column Starter Fixing – 1 carpenter + 2 Helpers – 6 Nos /day

THUMB RULES FOR CIVIL WORKS LABOUR PRODUCTIVITY Form Work Making Beam sides -1 Carpenter +1 Helper – 6 Sqm /day Column Boxes - 1 Carpenter +1 Helper – 3 Sqm /day Starter -1 Carpenter + 1Helpers - 5 Nos /day

THUMB RULES FOR CIVIL WORKS LABOUR PRODUCTIVITY Concreting Slab & Beams -1 Mason +1 Helper – 20 Cum /day

THUMB RULES FOR CIVIL WORKS LABOUR PRODUCTIVITY Block Works Block Works -1 Mason +1.5 Helper – ( 6 – 8 ) Sqm/day

THUMB RULES FOR CIVIL WORKS LABOUR PRODUCTIVITY Plastering Works Internal Plastering -1 Mason +1.5 Helper – 10 Sqm/day External Plastering -1 Mason +1.5 Helper – 12 Sqm/day (Per Coat ) Ceiling Plastering -1 Mason +1.5 Helper – ( 10 – 12 ) Sqm/day Corner beading Fixing -1 Mason +1 Helper – 7 Nos /day Mesh Fixing & Packing -2 Mason +1 Helper – 60 Running Feet /day

THUMB RULES FOR CIVIL WORKS LABOUR PRODUCTIVITY Earth Work Excavation Manual Excavation -2 Labours – 100 Cft /day Machine Operated (Poclain)- 60 Cum/Hr

THUMB RULES FOR CIVIL WORKS LABOUR PRODUCTIVITY MS Works Window Grill Fixing - 1 Mason +1.5 Helper - 3 Nos /day (Size -1800 X 1400) Balcony Handrail Fixing - 1 Mason +1.5 Helper - 5 Nos /day (2400 X 900 mm)

THUMB RULES FOR CIVIL WORKS LABOUR PRODUCTIVITY Water Proofing Works Horizontal Membrane Application -1 Applicator + 1 Helper – 150 Sqm /day Vertical Membrane Application -1 Applicator + 2 Helper – 50 Sqm /day Brush On Application -1 Applicator + 1 Helper – 20 Sqm /day (1 Coat) Bore Packing -1 Applicator +1 Helper – 3 Nos /day

THUMB RULES FOR CIVIL WORKS LABOUR PRODUCTIVITY Plumbing Works Toilet Chasing -1 Chipper – 7 Rmt /day Waterline Fixing - 1 Plumber + 1.5 Helper – 3 Toilets /day Sanitary Line Fixing -1 Plumber + 2 Helper – 3 Toilets/day Sanitary & CP Fittings -1.5 Plumber + 3 Helper – 3 Toilets & 1 kitchen /day

THUMB RULES FOR CIVIL WORKS LABOUR PRODUCTIVITY Electrical Works Box Fixing (Marking + Chasing + Fixing + Leveling ) -1 Skilled Eletrician+2 Semi Skilled Electrician -1 Flat / 3 days Note – 3 bedroom flat with around 50 Boxes

THUMB RULES FOR CIVIL WORKS LABOUR PRODUCTIVITY Tiling Works Toilet Dado - 80 Sft /mason /day Door Jambs - 30 Rft /mason /day Toilet Skirting - 45 Rft /mason /day Toilet Flooring - 90 Sft /mason /day Balcony Skirting - 50 Rft /mason /day Vitrified Flooring (Straight Joints)-100 Sft /mason/day Vitrified Flooring (Diagonal Joints)- 90 Sft /mason/day Vitrified Skirting - 70 Rft /mason /day Joint Filling -100 Sft /mason/day Roof Tiling -150 Sft /mason/day

THUMB RULES FOR CIVIL WORKS LABOUR PRODUCTIVITY Granite & Marble Works Hand Cutting - 150 Rft /mason /day Machine Cutting - 450 Rft /mason /day Groove Cutting - 200 Rft/mason /day Indian & Italian Marble ,Granite Flooring - 60 Sft / mason /day Staircase - 50 S ft/mason /day Lift Cladding -50 Sft /mason/day Joint Filling -100 Sft /mason/day Floor Polishing -100 Sft/mason/day Half & Full Nosing Making -60 Rft/mason/day Nosing (Champhering) Making -200 Rft/mason/day Half & Full Nosing Polishing – 35 Rft/mason/day