transformer sizing for starting motor.pptx

abdelmalekaep 50 views 20 slides Aug 19, 2024
Slide 1
Slide 1 of 20
Slide 1
1
Slide 2
2
Slide 3
3
Slide 4
4
Slide 5
5
Slide 6
6
Slide 7
7
Slide 8
8
Slide 9
9
Slide 10
10
Slide 11
11
Slide 12
12
Slide 13
13
Slide 14
14
Slide 15
15
Slide 16
16
Slide 17
17
Slide 18
18
Slide 19
19
Slide 20
20

About This Presentation

Sizing transformer


Slide Content

T R A N S F O R M E R M V A S I Z I N G U S I N G E T A P B y W aqar H u ss a i n Electrical Dept.

 In ower s stems transformer is one of man devices whose proper size is critical to the design of a power delivery system.  ETAP has com lied the information contained on standards ANSI – IEEE C57, IEC 60076-2 and IEC 60726 into a program that can easily determine the proper size of a power transformer

  r i n h f ll w i n f r E T A P k i n n i for trafo MVA sizing     Altitude    Type (dry or liquid fill)  Expected future growth  Short circuit requirement (trafo impedence and BIL)

  The two winding transformer MVA sizing calculation sizes the following  parameters of a transfomer  Rated MVA  Maximum MVA  Percentage impedance Maximum MVA is 1.25 times the rated MVA for ONAN – ONAF trafo.

. Transformer Loading   This section allows you to find the operating load ca cu a e rom oa ow ana ys s or connec e load to this transformer and then use either load for sizin ur oses   Also you can manually enter the loading for the transformer While sizing transformer based on connected load, spares can also be included

. Load Variation  Growth Factor – For allowance for future growth. Growth transformer. If “Use growth factor for max MVA” is checked, then it is used for calculating the max MVA  Load Factor – is 100 % if the transformer carries required load continuously all the time

. Installation  ETAP adjusts the calculated required Rated MVA b a s e d o n t r a fo ’ s a l t i t u d e v a l u e . F o r e x a m l e f o r L i u i d Immersed Forced Air Cooled trafo, the MVA rating is derated by factor 0.5 % for every 330 ft above 3300 .  Ambient Temp. ETAP adjusts the required Rated MVA

. Im edance  B a s ic I m u l s e L ev e l B I L L i m i t - E T A P u t i l i z e s t h i s value for determining the trafo minimum impedance according to ANSI – IEC standards  Limit Short Circuit kA – If this option is checked, then ETAP calculates % impedance based on short circuit ,

.   Larger size, Required size or smaller size

   Type (Liquid fill or Dry) , …  Class (ONAN, ONAN-ONAF, OFAF etc …)    Primary Winding kV rating 

   One of the factors to be considered while sizing a trafo is the voltage drop on start.  According to IEEE Brown Book, the voltage at terminals of starting motor should not fall below 80% of rated voltage for typical NEMA design B motors  T h i s v o l t a g e d r o p i s p r o p o r t i o n a l t o t h e r e g u l a t i o n o f t r a f o d u r i n g m o t o r s t a r t  The voltage drop at trafo secondary (regulation) during motor start is inversely proportional to trafo short circuit kVA and directly proportional to motor starting kVA  The Transformer MVA Sizing Module of ETAP does not take into account this factor. The regulation of trafo can be checked by Motor Starting Study on ETAP

  A roximate   volta e   dro   on   the   transformer   secondar   can   be   calculated   by   the   following   formula Where =   P   =   Peak   Load   on   trafo in   kVA other   than   largest   Motor   S   =   Short   circuit   capacity   of    trafo in   kVA

UCH2 Unit Auxiliary Transformer sizing using ETAP

  – Standard: IEC Type: Liquid Fill Sub type: mineral oil ass:  - emp. r se: Primary V = 14.5 kV Sec. V = 6.6 kV

–  Plant ETAP model a e v n a d l u o a p t e e r a c o t i n g n e l o c t e a d d o n a transformer Unit Auxiliary transformer to be sized Lum 1 of 13869 kVA represents the UCH2 operating BOP load other than 1 No. circulation water pump motor. The lump load contains all and loading factors of  different loads

   Based on Operating  rans ormer oa , growth factor (for max MVA or ONAF) and 28 degree C ambient tem . , the recommended size by ETAP is 20-25 MVA at ONAN-ONAF  Here worst case load is considered for GT, HRSG , by HET. (This load is included as “lump 1” in ETAP model)

U C H 2 L O A D F L O W A T 3 D I FF E R E N T U N I T A U X . T R A F O R A T I N G S – W O R S T C A S E L O A D I N G 16 ‐ 20   MVA   trafo 20 ‐ 25   MVA   trafo 25 ‐ 31.5   MVA   trafo %   Z   =   10,   X\R   =   22.2 %   Z   =   10,   X\R   =   22.2 %   Z   =   10,   X\R   =   22.2 Trafo   Input   kVA 16198 16046 15932 Trafo   Output   kVA 15217 15286 15339 – Increase in trafo output kVA as trafo rating is increased. ? Decrease in trafo input kVA as trafo rating is increased. ? Trafo % Z is taken rated trafo, ETAP performs Load flow at ONAN rating  20 % of the lump   model is static as contant at 10 %   regulation at trafo sec. the static load consumes more k V A

ETAP MOTOR START STUDY AT 3 DIFFERENT TRAFO R A T I N G S – N O R M AL C A S E L O A D I N G M o t o r   S t a r t i n g   A n a l y s i s For   Circulation   Water   Pump   Motor Load   Flow   before     M o t o r s t a r t Trafo   Input   MVA Load   Flow   at     M o t o r s t a r t   Motor   start   (steady   state) 16 ‐ 20   MVA   trafo %   Z   =   8,   X\R   =   22.2 . . . 20 ‐ 25   MVA   trafo %   Z   =   8,   X\R   =   22.2 20 ‐ 25   MVA   trafo %   Z   =   10,   X\R   =   22.2 13.655 21.345 15.333 13.632 20.865 15.277 If Normal loading is considered . , the sizing module recommends 16 – 20 M V A t r a f o

ETAP MOTOR START STUDY AT 3 DIFFERENT TRAFO R A T I N G S – N O R M AL C A S E L O A D I N G … . . C O N T D Motor   Starting   Analysis Motor   Terminal   Pump   Motor Trafo   sec.   Voltage   at   Motor   Start   Motor   Terminal     16 ‐ 20   MVA   trafo %   Z   =   8,   X\R   =   22.2 20 ‐ 25   MVA   trafo %   Z   =   8,   X\R   =   22.2 ‐ %   Z   =   10,   X\R   =   22.2 Start State 88.35% 92.09% 98.38% 90.34% 94.18% 99.49% 88.35% 92.09% 98.38% Motor Rated Voltage: Please note that the motor rated voltage is 6.3 kA where as the MV bus and trafo sec. rated voltage is 6.6 kV As per IEEE Standard 399-1997, IEEE Recommended Practice for Industrial and Commercial Power System Analysis (Brown Book), the Voltage at terminal of Motor during starting shall not fall below 80 % of rated voltage. Hence this condition is satistfied for all the three d iff e r e n t t r a f o r a ti n g s For ONAN – ONAF rated trafo, ETAP performs Motor Start at ONAN r a t i n g  

C AL C U L A T I O N O F T R A F O S E C . V O L T A G E A T M O T O R S T A R T U S I N G F O R M U LA …… C O M P A R I S O N calculated   using   ETAP T r a f o s e c .   V o l t a g e   a t   M o t o r   S t a r t   Formula Motor   Starting   Analysis   Pump   Motor 16 ‐ 20   MVA   trafo %   Z   =   8,   X\R   =   22.2 88.35% 87.36% 20 ‐ 25   MVA   trafo %   Z   =   8,   X\R   =   22.2 90.34% 89.89% 20 ‐ 25   MVA   trafo 88.35% 87.35%  Almost same results using  formula and ETAP, confirms the validity of the formula used in UCH2 trafo sizing  calculations   =   ,   =   . Starting kVA of motor = Full Load kVA x 6 = 11412 kVA Peak load on trafo excluding motor load = 13869 kVA