Report Week 3-4 2023 Divisi Eksplorasi Tanggal 14 – 27 januari

Summary # Production : Total Produksi Meter W-3 sebanyak 116 m ( 67.53 % ) dari total plan 171.78 m Total Hole Finish W-3 : 5 Hls Total Produksi Meter W-4 sebanyak 86 m ( 51.60% ) dari total plan 166.65 m Total Hole Finish W-4 sebanyak 3 Hls # Plan Next Week : Rig AFB01 drilling di Block 2B Lahan Pak Arham2 Rig AFB04 drilling di Block 2C Lahan Pak Asdar Re-survey borehole yang sudah Finish Preparasi Sample Wet dan Dry

Production Week 3

Production Week 3

Production Week 3

Production Week 4

Production Week 4

Drill Progress Summary

Drill Progress Map

Drill Plan Map Block 2C

Kendala Kendala Solusi Rig 01 Mesin Low Power Material Litologi mudah hancur dan loss Supply air untuk pengeboran tidak mencukupi Per kupu-kupu dan bearing pada Backend Innertube rusak sehingga hanya 2 innertube yang bisa dipakai (1 innertube tiap rig) Setel ulang tekanan hidrolik , mengganti V-belt kipas radiator dan filter oli Redrill kemudian bor secara hati-hati dan perlahan Menambah pompa sanchin ; 1 rig 1 pompa sanchin Menunggu PO barang datang Rig 04 Driller Cuti Supply air untuk pengeboran tidak mencukupi Digantikan sementara oleh Assisten Driller dengan didampingi oleh Geologist Menambah pompa sanchin ; 1 rig 1 pompa sanchin