PMP EXAM
SAMPLE Q & A
Following is an illustration of a project network activity
node that includes some information about activity D.
Given the information provided, what is the total float of
activity D?
A. 2
B. 14
C. 16
D. 18
HINT: Total float is calculated as the difference between
the late start and the early start or between the late finish
and the early finish. Question
The correct answer is C.
To answer this question, the first step is to
understand the meaning of the values displayed
on the network activity node. The accepted
convention is shown below, where:
ES = early start
EF = early finish
LS = late start
LF = late finish Answer
The total float can be calculated using either one of the
following two formulas:
Total Float = LF - EF
Total Float = LS - ES
To illustrate, we will use the first formula:
Total Float = LF - EF = 39 - 23 = 16
Here is the project schedule network activity node
filled in with the correct answer for total float, 16: Answer
All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge
(PMBOK® Guide) standard.
Stop by at free.pm-exam-simulator.com/ and try the
PM Exam Simulator free for 7 days.
We are a trusted and experienced education provider.