Free PMP Exam Sample Question of the Week

pmpodcast 19 views 6 slides Sep 15, 2025
Slide 1
Slide 1 of 6
Slide 1
1
Slide 2
2
Slide 3
3
Slide 4
4
Slide 5
5
Slide 6
6

About This Presentation

Here is our free PMP exam sample question for this week.

Stop by at https://free.pm-exam-simulator.com/ and try the PM Exam Simulator free for 7 days. We are a trusted and experienced education provider.


Slide Content

PMP EXAM
SAMPLE Q & A

The following table is an activity list that includes
the duration and predecessor for a series of
project activities.

What is the duration of the critical path?
A. 11
B. 14
C. 9
D. 13
Do you need to draw a project schedule network
diagram, or can you simply list all the possible the
sequences of paths with the given activities?
Which path constitutes the critical path? Question

The correct answer is B.
Using the critical path method may require drawing a project schedule network diagram, or listing
all the possible the sequences of paths with the given activities, then adding up the durations, and
knowing which path constitutes the critical path.

Given the activity list shown, you can see that:
Start serves as predecessor for both A and E, creating a divergence into two paths.
Activity A serves as predecessor for both B and C, creating another divergence.
Activity E serves as a predecessor for both B and F, creating another divergence. Answer

The project schedule network diagram is as follows. Answer

The resulting list of paths with their aggregated durations is below. The critical path is Start-E-B-D-
End, and the duration of the critical path with the data given is 14. Answer

All our questions are updated to the latest 
A Guide to the Project Management Body of Knowledge
(PMBOK® Guide) standard.
Stop by at free.pm-exam-simulator.com/ and try the
PM Exam Simulator free for 7 days.
We are a trusted and experienced education provider.