project management Master your project management Organize, execute, succeed!

simnikiwendlovu15 23 views 39 slides Aug 27, 2025
Slide 1
Slide 1 of 39
Slide 1
1
Slide 2
2
Slide 3
3
Slide 4
4
Slide 5
5
Slide 6
6
Slide 7
7
Slide 8
8
Slide 9
9
Slide 10
10
Slide 11
11
Slide 12
12
Slide 13
13
Slide 14
14
Slide 15
15
Slide 16
16
Slide 17
17
Slide 18
18
Slide 19
19
Slide 20
20
Slide 21
21
Slide 22
22
Slide 23
23
Slide 24
24
Slide 25
25
Slide 26
26
Slide 27
27
Slide 28
28
Slide 29
29
Slide 30
30
Slide 31
31
Slide 32
32
Slide 33
33
Slide 34
34
Slide 35
35
Slide 36
36
Slide 37
37
Slide 38
38
Slide 39
39

About This Presentation

Catchy Notes: Flashcards for Mastering Project Management in Construction!

project management notes


Slide Content

Flashcard 1: front: What is the definition of time management in project management? back: Time management is monitoring the duration it takes to carry out an activity, including the processes needed to manage the timely completion of a project.

Flashcard 2: front: What is the relationship between project management and time management? back: Time management is a crucial part of project management that ensures activities are completed on schedule to achieve project goals on time.

Flashcard 3: front: What are the main steps involved in the time management process? back: The main steps are: Plan Schedule Management, Define Activity, Sequence Activity, Estimate Activity Resources, Estimate Activity Duration, Develop the Schedule, and Control the Schedule.

Flashcard 4: front: What is involved in the "Plan Schedule Management" step? back: It involves developing and maintaining the schedule by outlining when activities should be done and ensuring policies and procedures are in place.

Flashcard 5: front: How is "Define Activity" performed in time management? back: By utilizing the Work Breakdown Structure (WBS) to identify and document what needs to be done to provide deliverables.

Flashcard 6: front: What does "Sequence Activity" mean? back: It means logically arranging and sequencing activities in the correct order to ensure proper flow.

Flashcard 7: front: Why is estimating activity resources important? back: Because it identifies the resources required for each activity to ensure proper planning and execution.

Flashcard 8: front: What does estimating activity duration involve? back: It involves determining the time required to complete an activity.

Flashcard 9: front: What is done during the "Develop the Schedule" process? back: Data is compiled to create the schedule, prioritizing activities to prevent delays.

Flashcard 10: front: What is the purpose of controlling the schedule? back: To monitor progress, update the schedule, and control any changes.

Flashcard 11: front: Give an example of defining an activity in a project. back: Activity: Dig & compact the foundation. Scope: Hire a TLB, excavate, and compact the foundation.

Flashcard 12: front: What is the importance of sequencing activities correctly? back: To allocate activities properly, identify relationships among them, and ensure a proper flow for project execution.

Flashcard 13: front: What is a network diagram in project time management? back: A network diagram outlines dependency determination between activities, showing relationships, leads, and lags with logical links.

Flashcard 14: front: What is a "lag" in project scheduling? back: Lag is the amount of time a successor activity should be delayed after its predecessor finishes (e.g., waiting for plaster to dry before moving in).

Flashcard 15: front: What is a "lead" in project scheduling? back: Lead is an overlap where a successor activity starts before the predecessor finishes (e.g., starting floor tiling before the building is fully finished).

Flashcard 16: front: How should activities be prioritized when determining the order of execution? back: Activities with shorter duration should be carried out before those with longer duration, considering float time available.

Flashcard 17: front: How do you calculate the duration needed to complete an activity when multiple workers are involved? back: Duration = Total work volume / (Work capacity per worker * Number of workers). For example, casting 3000m³ concrete with 6 workers each covering 500m³ results in 1 day.

Flashcard 18: front: What is the Program Evaluation Review Technique (PERT) used for? back: PERT is used to estimate project duration when activity durations are uncertain, using optimistic, most likely, and pessimistic time estimates.

Flashcard 19: front: Name some schedule techniques used in project time management. back: Gantt charts, network diagrams, Critical Path Method (CPM), resource optimization, modeling techniques, and schedule compression (crashing and fast-tracking).

Flashcard 20: front: What is a Gantt chart? back: A Gantt chart is a simple method to represent project plans using bars to indicate the start and end dates of activities and their progress.

Flashcard 21: front: How do Gantt charts indicate activities with shorter durations? back: Using diamond or triangle symbols on the chart.

Flashcard 22: front: What is the Critical Path Method (CPM)? back: CPM identifies the longest path of activities from start to finish that determines the project duration and highlights critical activities.

Flashcard 23: front: Why must critical path activities be closely monitored? back: Because any delay in a critical path activity delays the entire project.

Flashcard 24: front: How is the critical path identified using a network diagram? back: By applying forward and backward passes to calculate early start, early finish, late start, and late finish dates, and determining float times.

Flashcard 25: front: What happens if an activity has more than one predecessor? back: The predecessor with the latest finish date determines the start date of the successor activity.

Flashcard 26: front: What happens if an activity has more than one successor? back: The successor with the latest start date determines the latest finish date of the predecessor.

Flashcard 27: front: What is a near critical path? back: A path with a duration close to the critical path, which could become critical if delayed.

Flashcard 28: front: How do you perform a forward pass in a network diagram? back: Finish Date = Start Date + Duration.

Flashcard 29: front: How do you perform a backward pass in a network diagram? back: Start Date = Late Finish – Duration.

Flashcard 30: front: What are some methods to reduce project duration? back: Allocate more resources (e.g., subcontracting), motivate the team (bonuses), reduce project scope, and use crashing by allocating more expensive resources.

Flashcard 31: front: What is crashing in project time management? back: Crashing is completing an activity faster than normal by allocating additional costly resources to shorten the duration.

Flashcard 32: front: How is cost slope calculated in crashing? back: Cost slope = (Crashing Cost – Normal Cost) / (Normal Time – Crashing Time).

Flashcard 33: front: What is the significance of cost slope in crashing? back: It shows the rate of increase in cost per unit of time saved by crashing an activity.

Flashcard 34: front: What information is needed to perform network analysis for a project? back: Activity durations, predecessors, resources (laborers), and costs to determine critical path and float.

Flashcard 35: front: In the example given, how long is the duration of the dam construction project? back: The project is expected to run over a period of 13 months.

Flashcard 36: front: What is float in project management? back: Float is the amount of time an activity can be delayed without affecting the project completion date.

Flashcard 37: front: Why is the network diagram considered the correct output of activity sequencing? back: Because it visually represents relationships, dependencies, leads, and lags between activities in logical order.

Flashcard 38: front: What should be done if an activity on the critical path takes longer than anticipated? back: The entire project will be delayed; therefore, focus should be on managing and mitigating delays in critical path activities.

Flashcard 39: front: What is the role of monitoring and controlling the schedule? back: To track progress, update the schedule as needed, and manage changes to keep the project on time.