Over $400,000 worth of improvements were made to the 100-year-old school building during the Summer of 2025 as we celebrate its Centennial Anniversary. We have now made $1,200,000 of improvements to this historic building built in 1925 since the Summer of 2022.

This has made the building a more des...


Slide Content

Sarah A. Reed Children’s Center
Interior Improvements as of September 29, 2025
Gary L. Bukowski, MA, CFRE (AVP of Development at Sarah Reed)
(814) 835-7602 • [email protected]





$119,713 Interior Corridor, Flooring and Stairwell Improvements:
Remove old, torn carpeting from the 1
st
and 2
nd
floors, as well as the carpeting along the walls; install
beadboard along the interior 1
st
and 2
nd
floor corridors and paint the hallways; install new carpeting
throughout the 1
st
and 2
nd
floor hallways, offices and conference room; install new vinyl flooring in the
stairwells and replace old, broken stair tiles with new rubber tiles.
Week 1: June 9 – June 13, 2025












BEFORE

Week 2: June 16 – June 20, 2025

Week 3: June 23 – June 27, 2025 (Work on the flooring began June 26
th
)

Week 4: June 30, 2025 – July 3, 2025









Week 5: July 7, 2025 – July 11, 2025 (Corridor work was completed on July 10
th
)

Week 6: July 14, 2025 – July 18, 2025















Week 7: July 21, 2025 – July 25, 2025







Week 8: July 28, 2025 – August 1, 2025

Week 8: July 28, 2025 – August 1, 2025 (Continued)







Week 9: August 4, 2025 – August 8. 2025














Week 10: August 11, 2025 – August 15, 2025

Week 11: August 18 – August 22, 2025















Week 12: August 25 – August 29, 2025 and Finishing Touches on 9/26/2025 + New Exterior Railings!














These projects were completed September 26, 2025, wrapping up $400,000 of 2025 capital improvements to date.